R-17-02RESOLUTION NO. R-17-02
A RESOLUTION TO PROCEED WITH PRELIMINARY ENGINEERING
INCLUDING EVALUATION OF POTENTIAL STREET DESIGN MODIFICATIONS
FOR THE UNIVERSITY DRIVE EXTENSION PROJECT (UPC 109309)
WHEREAS, the City has developed a conceptual plan for the University
Drive Extension, which was submitted to VDOT as part of the Smart Scale
(previously HB2) funding application, which includes construction of a new
roadway between Fairfax Boulevard and Eaton Place north of University
Drive; and
WHEREAS, the property owners in the project area have been notified of the
project and invited to comment on it; and
WHEREAS, the estimated project costs including right of way/easement
acquisition and construction will be approximately $10,000,000; and
WHEREAS, the City applied for and received Smart Scale funds from the
Virginia Department of Transportation for the project; and
NOW THEREFORE, BE IT RESOLVED by the City Council of the City of
Fairfax, Virginia that the City Council approves the recommendation of staff to
proceed with the preliminary engineering including evaluation of potential street
design modifications for the University Drive Extension (UPC 109309).
Adopted this 24h day of January, 2017.
Attest:
City Clerk
The vote on the motion to approve was recorded as follows:
VOTE:
Councilmember DeMarco
Aye
Councilman Greenfield
Aye
Councilman Meyer
Aye
Councilmember Miller
Aye
Councilmember Schmidt
Nay
Councilmember Stehle
Aye